Minister Inspects Butler Railway Station Works

Minister Inspects Butler Railway Station Works

Western Australia Minister for Transport Troy Buswell

Butler Station Moves Step Closer As Track Laid

Victor P Taffa

  • Track-laying starts for Butler railway extension
  • Services expected to start in late 2014

Transport Minister Buswell today inspected progress on the $240 Million railway expansion project to extend the Joondalup Line 7.5 km north, to the new Butler Station.

The visit coincides with the start of work to lay the track and install the overhead traction wiring equipment.

The track work starts near the southern end of the Nowergup railcar depot, just north of the existing end-station at Clarkson, and progresses north.

In this $24 Million part of the Butler project, 26,500 concrete sleepers, 40,000 tonnes of ballast and 1,750 tonnes of steel rail will be laid in anticipation of the first passenger train to visit Butler Station in late 2014.

The work involves building a total 13 km of track including single as well as double track from Clarkson Station to Butler Station and 5.4 km of track within the Nowergup railyard.

The track work, being carried out under contract by John Holland, has started as the project’s major civil contract covering earthworks and the construction of three bridges comes to an end.

The new part of the Joondalup Line is expected to be operating by December 2014.

Fact File

  • 26,500 concrete sleepers, 40,000 tonnes of ballast and 1,750 tonnes of steel to be laid